Skip to main content

ENTERGY LOUISIANA CEO LETS IT SLIP ON META'S ELECTRICITY DEMANDS

(The Center Square) — Entergy Louisiana CEO Phillip May accidentally disclosed Tuesday that Meta’s Richland Parish data center is expected to draw 4,500 megawatts of electricity, revealing for the first time a closely guarded figure that shows the extraordinary scale of the project’s power demand.

For perspective, 4,500 MW is about four times the peak electricity demand of the entire city of New Or…

PO Box 910 | 238 Market Street | Jennings, LA 70546 | 337.824.3011
PRINT ISSN 3069-4949
ONLINE ISSN 3069-4957